Beatrice 400kV Substation
North Scotland, SSEN Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Beatrice Sync Comp | TINZ PROGRAMME 1 PROJECTCO 3 LIMITED | Other | 0 | Connected | Not stated | Built |
| Beatrice Wind Farm | BEATRICE OFFSHORE WINDFARM LIMITED | Offshore wind | 0 | Connected | Not stated | Built |
Recent changes
- Beatrice Sync CompNorth Scotland, OtherConnection date removed (was 31 May 2024)
- Beatrice Sync CompNorth Scotland, OtherStatus changed from Scoping to Built
- Beatrice Sync CompNorth Scotland, OtherCapacity changed from 1 MW to 0 MW
- Beatrice Sync CompNorth Scotland, OtherConnection date moved from 31 Jul 2023 to 31 May 2024 (+10 months)+10 mo
- Beatrice Sync CompNorth Scotland, OtherTransmission owner changed from OFTO to SHET
- Beatrice Sync CompNorth Scotland, OtherConnection point changed from Beatrice 400kV Onshore substation to Beatrice 400kV Substation
- Beatrice Wind FarmNorth Scotland, Offshore windConnection point changed from Beatrice 33/132kV Offshore Substations to Beatrice 400kV Substation
- Beatrice Sync CompNorth Scotland, OtherAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?