Beatrice Sync Comp
TINZ PROGRAMME 1 PROJECTCO 3 LIMITED at Beatrice 400kV Substation
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Technology
- Reactive compensation
- Total capacity
- 0 MW
- Connected now
- 0 MW
- Still to connect
- 0 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-001757
- In the register since
- December 2021
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Jul 2025 registerConnection date removed (was 31 May 2024)
- 29 Jul 2025 registerStatus changed from Scoping to Built
- 26 Apr 2024 registerCapacity changed from 1 MW to 0 MW
- 26 Apr 2024 registerConnection date moved from 31 Jul 2023 to 31 May 2024 (+10 months)
- 26 Mar 2024 registerTransmission owner changed from OFTO to SHET
- 23 Dec 2022 registerConnection point changed from Beatrice 400kV Onshore substation to Beatrice 400kV Substation
- 31 Dec 2021 registerAdded to the register
Also at Beatrice 400kV Substation
Substation view1 other project, 0 MW still to connect at this substation in total.