Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Armadale 400kv Substation

South Scotland, SP Energy Networks

1project in the register
300 MWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Elmya Bathgate BESSRPC ELMYA CARNATION BATHGATE LIMITEDStorage30031 Oct 2031Gate 1Scoping

Left the register since January 2021: Armadale Wind Farm (99 MW).

Recent changes

  • Elmya Bathgate BESSSouth Scotland, StorageAdded to the registerNew
  • Elmya Bathgate BESSSouth Scotland, StorageLeft the register (300 MW from 31 Oct 2031)300 MW
  • Elmya Bathgate BESSSouth Scotland, StorageMarked as Gate 1
  • Elmya Bathgate BESSSouth Scotland, StorageCustomer changed from RPC ELMYA CARNATION DEVCO LIMITED to RPC ELMYA CARNATION BATHGATE LIMITED
  • Elmya Bathgate BESSSouth Scotland, StorageTransmission owner changed from SHET to SPT
  • Armadale Wind FarmNorth Scotland, Storage with solar or windLeft the register (99 MW from 1 Aug 2027)99 MW
  • Elmya Bathgate BESSSouth Scotland, StorageAdded to the registerNew
  • Armadale Wind FarmNorth Scotland, Storage with solar or windConnection point changed from Armadale 132/33kV Substation to Armadale 400kv Substation
  • Armadale Wind FarmNorth Scotland, Storage with solar or windTechnology changed from Onshore wind to Storage, Onshore wind
  • Armadale Wind FarmNorth Scotland, Storage with solar or windConnection date moved from 1 Jun 2026 to 1 Aug 2027 (+14 months)+14 mo
  • Armadale Wind FarmNorth Scotland, Storage with solar or windConnection point changed from Armadale Windfarm 132/33kV Substation to Armadale 132/33kV Substation
  • Armadale Wind FarmNorth Scotland, Storage with solar or windConnection date moved from 31 Aug 2025 to 1 Jun 2026 (+9 months)+9 mo
  • Armadale Wind FarmNorth Scotland, Storage with solar or windCustomer changed from BROOKFIELD RENEWABLE UK LIMITED to WIND DEVELOPMENT HOLDINGS LIMITED
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO