Transmission / Projects / North Scotland

Armadale Wind Farm

WIND DEVELOPMENT HOLDINGS LIMITED at Armadale 400kv Substation

Connection date
Left 30 Sep 2025
Gate
Not stated
Status
Awaiting Consents
Technology
Storage + Onshore wind
Total capacity
99 MW
Connected now
0 MW
Still to connect
99 MW
Transmission owner
SSEN Transmission (SHET)
Agreement type
Direct Connection
Region
North Scotland
Project number
PRO-000557
In the register since
January 2021 or earlier

Change history

Every change to this project across 146 registers from 29 Jan 2021 to 20 Oct 2026.

  • 30 Sep 2025 register
    Left the register (99 MW from 1 Aug 2027)
  • 31 May 2024 register
    Connection point changed from Armadale 132/33kV Substation to Armadale 400kv Substation
  • 26 Mar 2024 register
    Technology changed from Onshore wind to Storage, Onshore wind
  • 30 May 2023 register
    Connection date moved from 1 Jun 2026 to 1 Aug 2027 (+14 months)
  • 23 Dec 2022 register
    Connection point changed from Armadale Windfarm 132/33kV Substation to Armadale 132/33kV Substation
  • 25 Feb 2022 register
    Connection date moved from 31 Aug 2025 to 1 Jun 2026 (+9 months)
  • 29 Jun 2021 register
    Customer changed from BROOKFIELD RENEWABLE UK LIMITED to WIND DEVELOPMENT HOLDINGS LIMITED

Also at Armadale 400kv Substation

Substation view

1 other project, 300 MW still to connect at this substation in total.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO