NatPower Oswestry Green Energy Park
- Connection date
- 31 Oct 2037
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 1,000 MW
- Connected now
- 0 MW
- Still to connect
- 1,000 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-005057
- In the register since
- February 2025
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 13 Mar 2026 registerConnection point changed from Oswestry Substation to Cheshire Connection Node A2 400kV
- 13 Mar 2026 registerMarked as Gate 1
- 28 Feb 2025 registerAdded to the register
Also at Cheshire Connection Node A2 400kV
Substation view1 other project, 1.6 GW still to connect at this substation in total. 550 MW is due to connect here before this project’s connection date of 31 Oct 2037.