New Marton GEC
NEW MARTON GREEN ENERGY CENTRE LIMITED at Cheshire Connection Node A2 400kV
- Connection date
- 30 Oct 2037
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Demand + Storage + Solar + Reactive compensation
- Total capacity
- 550 MW
- Connected now
- 0 MW
- Still to connect
- 550 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004796
- In the register since
- January 2025
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Dec 2025 registerMarked as Gate 1
- 30 Sep 2025 registerConnection point changed from New Marton 400kV Substation to Cheshire Connection Node A2 400kV
- 29 Apr 2025 registerConnection date moved from 11 Apr 2025 to 30 Oct 2037 (+151 months)
- 31 Jan 2025 registerAdded to the register
Also at Cheshire Connection Node A2 400kV
Substation view1 other project, 1.6 GW still to connect at this substation in total.