Melton Mowbray Solar
Cubico UK Development Limited at West Anglia Connection Node I 400kV substation
- Connection date
- 30 Oct 2037
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 340 MW
- Connected now
- 0 MW
- Still to connect
- 340 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-005004
- In the register since
- January 2025
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Dec 2025 registerMarked as Gate 1
- 31 Jan 2025 registerAdded to the register
Also at West Anglia Connection Node I 400kV substation
Substation view2 other projects, 2.3 GW still to connect at this substation in total. 2 GW is due to connect here before this project’s connection date of 30 Oct 2037.