Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Cubico UK Development Limited

Customer named in the TEC register

4projects in the register
640 MWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

Projects

ProjectConnection siteTechnologyQueued MWConnection dateGateStatus
Daviot Windfarm BEGAINVERNESS 132/33KV GRID SUPPLY POINT SUBSTATIONStorage with solar or wind4531 Oct 2030Gate 1Scoping
Woodland RidgeHawick 132kV SubstationStorage with solar or wind1503 Jul 2034Gate 1Scoping
Old Stoke Rd BESSNorth Anglia Connection Node A 132kV SubstationStorage10531 Oct 2034Not statedScoping
Melton Mowbray SolarWest Anglia Connection Node I 400kV substationStorage with solar or wind34030 Oct 2037Gate 1Scoping

Left the register since January 2021: Daviot Windfarm (45 MW).

Recent changes

  • Daviot Windfarm BEGANorth Scotland, Storage with solar or windConnection point changed from Inverness GSP to INVERNESS 132/33KV GRID SUPPLY POINT SUBSTATION
  • Daviot Windfarm BEGANorth Scotland, Storage with solar or windMarked as Gate 1
  • Woodland RidgeSouth Scotland, Storage with solar or windMarked as Gate 1
  • Melton Mowbray SolarEngland and Wales, Storage with solar or windMarked as Gate 1
  • Daviot WindfarmNorth Scotland, Storage with solar or windLeft the register (45 MW from 31 Mar 2031)45 MW
  • Daviot Windfarm BEGANorth Scotland, Storage with solar or windAdded to the registerNew
  • Old Stoke Rd BESSEngland and Wales, StorageAdded to the registerNew
  • Woodland RidgeSouth Scotland, Storage with solar or windAdded to the registerNew
  • Melton Mowbray SolarEngland and Wales, Storage with solar or windAdded to the registerNew
  • Daviot WindfarmNorth Scotland, Storage with solar or windConnection point changed from Inverness GSP to Daviot 132/33kV Substation
  • Daviot WindfarmNorth Scotland, Storage with solar or windCustomer changed from PEEL CUBICO RENEWABLES LIMITED to CUBICO UK DEVELOPMENT LIMITED
  • Daviot WindfarmNorth Scotland, Storage with solar or windAdded to the registerNew
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO