Netherton BESS
- Connection date
- 31 Oct 2033
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 400 MW
- Connected now
- 0 MW
- Still to connect
- 400 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-004626
- In the register since
- June 2025
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 20 Mar 2026 registerMarked as Gate 1
- 29 Aug 2025 registerConnection point changed from Netherton 400kV Substation to Longside 400kV Substation
- 27 Jun 2025 registerAdded to the register
Also at Longside 400kV Substation
Substation view4 other projects, 5.5 GW still to connect at this substation in total. 1 GW is due to connect here before this project’s connection date of 31 Oct 2033.
- Marram Wind Offshore Wind FarmMarramwind Limited, Offshore wind, Not statedOct 20313 GW
- Broadshore Offshore Wind FarmBroadshore Offshore Wind Farm Limited, Offshore wind, Not statedOct 2033900 MW
- Muir Mhor Offshore Wind FarmMUIR MHÒR OFFSHORE WIND FARM LIMITED, Offshore wind, Not statedOct 20331 GW
- Netherton Hub BessField Netherton Ltd, Storage, Gate 1Oct 2033200 MW