QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / North Scotland

Muir Mhor Offshore Wind Farm

MUIR MHÒR OFFSHORE WIND FARM LIMITED at Longside 400kV Substation

Connection date
31 Oct 2033
Gate
Not stated
Status
Awaiting Consents
Planning consent
Application submitted 5 Dec 2024
Marine Scotland · Source: REPD
Technology
Offshore wind
Total capacity
1,000 MW
Connected now
0 MW
Still to connect
1,000 MW
Transmission owner
SSEN Transmission (SHET)
Agreement type
Direct Connection
Region
North Scotland
Project number
PRO-001698
In the register since
November 2021

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 18 Sep 2026 register
    Status changed from Scoping to Awaiting Consents
  • 30 Jan 2026 register
    Connection point changed from Cirrus Offshore Windfarm Substation to Longside 400kV Substation
  • 29 Aug 2023 register
    Renamed from Cirrus Offshore Wind Farm
  • 29 Aug 2023 register
    Customer changed from FRED OLSEN SEAWIND LIMITED to MUIR MHÒR OFFSHORE WIND FARM LIMITED
  • 23 Dec 2022 register
    Substation name updated in the register (from Cirrus Offshore Windfarm to Cirrus Offshore Windfarm Substation)
  • 28 Jan 2022 register
    Customer changed from FRED. OLSEN RENEWABLES LIMITED to FRED. OLSEN SEAWIND LIMITED
  • 30 Nov 2021 register
    Added to the register

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO

Planning consent

The planning decision or stage for this project, from DESNZ’s Renewable Energy Planning Database (REPD), July 2026 edition, with the planning authority and its reference. QueueWatch matched the project to that record. NESO’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.