NatPower-Medway Energy Park
Old Rides Energy Storage Limited at North Kent Connection Node A 400kV Substation
- Connection date
- 31 Oct 2034
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 1,000 MW
- Connected now
- 0 MW
- Still to connect
- 1,000 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004583
- In the register since
- June 2025
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 19 Jun 2026 registerMarked as Gate 1
- 13 Jan 2026 registerCustomer changed from NATPOWER MARINE UK LIMITED to Old Rides Energy Storage Limited
- 29 Aug 2025 registerRenamed from NatPower Medway Green Energy Park
- 29 Jul 2025 registerConnection point changed from Kemsley 400kV Substation to North Kent Connection Node A 400kV Substation
- 27 Jun 2025 registerAdded to the register
Also at North Kent Connection Node A 400kV Substation
Substation view1 other project, 1.3 GW still to connect at this substation in total. 280 MW is due to connect here before this project’s connection date of 31 Oct 2034.