Alcemi Ridham Docks BESF
Alcemi Storage Developments 23 Ltd at North Kent Connection Node A 400kV Substation
- Connection date
- 31 Oct 2033
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 280 MW
- Connected now
- 0 MW
- Still to connect
- 280 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003211
- In the register since
- January 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 19 Dec 2025 registerMarked as Gate 1
- 29 Jul 2025 registerConnection date moved from 31 Oct 2037 to 31 Oct 2033 (−48 months)
- 27 Sep 2024 registerConnection point changed from Kemsley 400kV Substation to North Kent Connection Node A 400kV Substation
- 27 Sep 2024 registerConnection date moved from 31 Oct 2031 to 31 Oct 2037 (+72 months)
- 30 Jan 2024 registerAdded to the register
Also at North Kent Connection Node A 400kV Substation
Substation view1 other project, 1.3 GW still to connect at this substation in total.