Middle Farm Chollerton
- Connection date
- 30 Oct 2035
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 240 MW
- Connected now
- 0 MW
- Still to connect
- 240 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004344
- In the register since
- January 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Feb 2026 registerMarked as Gate 1
- 24 Dec 2024 registerConnection date moved from 31 Oct 2036 to 30 Oct 2035 (−12 months)
- 26 Nov 2024 registerCustomer changed from INTEGRUM RENEWABLE ENERGY LTD to ENRAY POWER LTD
- 30 Jul 2024 registerConnection point changed from Fourstones GSP to Borders Connection Node A 400kV
- 30 Jan 2024 registerAdded to the register
Also at Borders Connection Node A 400kV
Substation view1 other project, 440 MW still to connect at this substation in total.