Lynefield BESS
WINDEL GRID 1 LIMITED at Borders Connection Node A 400kV Substation
- Connection date
- 30 Oct 2035
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003555
- In the register since
- September 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 1 May 2026 registerMarked as Gate 1
- 24 Dec 2024 registerConnection date moved from 31 Oct 2033 to 30 Oct 2035 (+24 months)
- 27 Sep 2024 registerConnection point changed from Blyth 400kV Substation to Borders Connection Node A 400kV Substation
- 29 Sep 2023 registerAdded to the register
Also at Borders Connection Node A 400kV
Substation view1 other project, 440 MW still to connect at this substation in total.