Meall Buidhe Wind Farm
- Connection date
- 31 Oct 2032
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Granted on appeal 14 Jun 2023
Highland, reference 20/02659/FUL · Source: REPD - Technology
- Onshore wind
- Total capacity
- 40 MW
- Connected now
- 0 MW
- Still to connect
- 40 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-004198
- In the register since
- October 2024
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 19 Jun 2026 registerConnection point changed from Shin GSP to Shin 1 GSP
- 29 Oct 2024 registerAdded to the register
Also at Shin 1 GSP
Substation view2 other projects, 164 MW still to connect at this substation in total. 50 MW is due to connect here before this project’s connection date of 31 Oct 2032.