Allt an Tuir Renewable Energy Park
- Connection date
- 30 Jun 2031
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Solar + Onshore wind
- Total capacity
- 50 MW
- Connected now
- 0 MW
- Still to connect
- 50 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-001819
- In the register since
- June 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 19 Jun 2026 registerConnection point changed from Shin GSP to Shin 1 GSP
- 27 Sep 2024 registerConnection date moved from 30 Sep 2027 to 30 Jun 2031 (+45 months)
- 27 Sep 2024 registerTechnology changed from Onshore wind to Storage, Solar, Onshore wind
- 26 Mar 2024 registerRenamed from Glenrossal Wind Farm
- 31 Mar 2023 registerCustomer changed from GLENROSSAL WIND FARM LIMITED to ALLT AN TUIR RENEWABLE ENERGY PARK LIMITED
- 23 Dec 2022 registerSubstation name updated in the register (from Shin 132/33kV GSP to Shin GSP)
- 30 Jun 2022 registerAdded to the register
Also at Shin 1 GSP
Substation view2 other projects, 164 MW still to connect at this substation in total.