Swansea North-Rhigos Solar& BESS & Wind
TYLER HILL CONSULTING LIMITED at South Wales West Connection Node A 400kV Substation
- Connection date
- 30 Oct 2037
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar + Onshore wind
- Total capacity
- 400 MW
- Connected now
- 0 MW
- Still to connect
- 400 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004099
- In the register since
- August 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 17 Mar 2026 registerMarked as Gate 1
- 30 May 2025 registerCustomer changed from TYLER HILL RENEWABLES LIMITED to TYLER HILL CONSULTING LIMITED
- 27 Aug 2024 registerAdded to the register
Also at South Wales West Connection Node A 400kV Substation
Substation view5 other projects, 1.8 GW still to connect at this substation in total.
- Nant HelenSOLAR SECURITIES LIMITED, Storage with solar or wind, Gate 1Oct 2037500 MW
- Rhigos BESSREWE 11 Limited, Storage, Gate 1Oct 2037200 MW
- Rhigos BESSKONA ASSET 4 LIMITED, Storage, Not statedOct 2037225 MW
- Lightsource Rhigos BESSLightsource Renewable UK Development Limited, Storage, Not statedOct 2037300 MW
- TH Maes MelinFRV Powertek Limited, Storage, Not statedOct 2037200 MW