- Connection date
- 31 Oct 2034
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Granted 4 Jul 2025
Mid Suffolk, reference DC/24/05535 · Source: REPD - Technology
- Storage
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003964
- In the register since
- February 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Aug 2025 registerCustomer changed from FIELD DEVCO LTD to Field Yaxley Ltd
- 29 Oct 2024 registerConnection point changed from Yaxley 400kV Substation to North Anglia Connection Node E 400kV Substation
- 27 Sep 2024 registerConnection date moved from 31 Oct 2035 to 31 Oct 2034 (−12 months)
- 27 Feb 2024 registerAdded to the register
Also at North Anglia Connection Node E 400kV Substation
Substation view6 other projects, 2.4 GW still to connect at this substation in total.
- Dove SolarRWE Renewables UK Solar and Storage Limited, Storage with solar or wind, Gate 1Oct 2034500 MW
- EPL SuffolkEPL NEWCO9 LIMITED, Storage with solar or wind, Gate 1Oct 2034480 MW
- Lightsource Yaxley PVLightsource Renewable UK Development Limited, Storage with solar or wind, Gate 1Oct 2034240 MW
- Noventum YaxleyNOVENTUM POWER SOLAR 3 LIMITED, Storage with solar or wind, Gate 1Oct 2034150 MW
- YaxleyCONNECTID 2 LIMITED, Storage with solar or wind, Not statedOct 2034520 MW
- Zenobe Yaxley BESSZENOBE ENERGY LIMITED, Storage, Not statedOct 2034300 MW