EcoStocksbridge
Econergy International Limited at Stocksbridge 400kV Substation
- Connection date
- 30 Oct 2036
- Gate
- Not stated
- Status
- Scoping
- Technology
- Demand + Storage + Solar
- Total capacity
- 249 MW
- Connected now
- 0 MW
- Still to connect
- 249 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003789
- In the register since
- June 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Jul 2025 registerTechnology changed from Storage, Solar to Demand, Storage, Solar
- 30 Jun 2023 registerAdded to the register
Also at Stocksbridge 400kV Substation
Substation viewNo other projects in the register at this connection point.