Kellwood Road BESS
- Connection date
- 30 Jul 2030 +33 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Planning consent
- Granted 15 Apr 2025
Dumfries and Galloway, reference 24/1075/FUL · Source: REPD - Technology
- Storage
- Total capacity
- 40 MW
- Connected now
- 0 MW
- Still to connect
- 40 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Embedded
- Region
- South Scotland
- Project number
- PRO-003710
- In the register since
- May 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Oct 2026 registerGiven a Gate 2 connection offer
- 4 Sep 2026 registerConnection date moved from 31 Oct 2027 to 30 Jul 2030 (+33 months)
- 25 Aug 2026 registerStatus changed from Scoping to Consents Approved
- 21 Nov 2025 registerCustomer changed from Geocore Ltd to Geocore (Kellwood) Ltd
- 31 Oct 2025 registerConnection point changed from Kellwood Road 33KV to Dumfries 132/33kV
- 27 Sep 2024 registerSubstation name updated in the register (from Kellwood Road 33KV Substation to Kellwood Road 33KV)
- 30 May 2023 registerAdded to the register
Also at Dumfries 132/33kV
Substation view2 other projects, 90 MW still to connect at this substation in total. 50 MW is due to connect here before this project’s connection date of 30 Jul 2030.