Geocore (Kellwood) Ltd
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Kellwood Road BESS | Dumfries 132/33kV | Storage | 40 | 30 Jul 2030 +33 mo | Gate 2 | Consents Approved |
Recent changes
- Kellwood Road BESSSouth Scotland, StorageGiven a Gate 2 connection offerGate 2
- Kellwood Road BESSSouth Scotland, StorageConnection date moved from 31 Oct 2027 to 30 Jul 2030 (+33 months)+33 mo
- Kellwood Road BESSSouth Scotland, StorageStatus changed from Scoping to Consents Approved
- Kellwood Road BESSSouth Scotland, StorageCustomer changed from Geocore Ltd to Geocore (Kellwood) Ltd
- Kellwood Road BESSSouth Scotland, StorageConnection point changed from Kellwood Road 33KV to Dumfries 132/33kV
- Kellwood Road BESSSouth Scotland, StorageSubstation name updated in the register (from Kellwood Road 33KV Substation to Kellwood Road 33KV)
- Kellwood Road BESSSouth Scotland, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?