Mooir Vannin Offshore Wind Farm Limited
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Isle of Man Offshore Wind Farm | IMW01 OFFSHORE 275/66KV OFFSHORE SUBSTATION | Offshore wind | 1,320 | 30 Sep 2037 −1 mo | Gate 1 | Scoping |
Recent changes
- Isle of Man Offshore Wind FarmEngland and Wales, Offshore windConnection date moved from 30 Jul 2037 to 30 Sep 2037 (+2 months)+2 mo
- Isle of Man Offshore Wind FarmEngland and Wales, Offshore windConnection date moved from 30 Oct 2037 to 30 Jul 2037 (−3 months)−3 mo
- Isle of Man Offshore Wind FarmEngland and Wales, Offshore windConnection point changed from Penwortham 400kV Substation to IMW01 OFFSHORE 275/66KV OFFSHORE SUBSTATION
- Isle of Man Offshore Wind FarmEngland and Wales, Offshore windMarked as Gate 1
- Isle of Man Offshore Wind FarmEngland and Wales, Offshore windCustomer changed from Orsted Isle of Man (UK) Limited to Mooir Vannin Offshore Wind Farm Limited
- Isle of Man Offshore Wind FarmEngland and Wales, Offshore windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?