Zenobe Spennymoor BESS
ZENOBE ENERGY LIMITED at Wearside Connection Node D 400kV Substation
- Connection date
- 30 Oct 2035 +12 months since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 300 MW
- Connected now
- 0 MW
- Still to connect
- 300 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003692
- In the register since
- July 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerConnection date moved from 30 Oct 2034 to 30 Oct 2035 (+12 months)
- 20 Mar 2026 registerMarked as Gate 1
- 29 Aug 2025 registerConnection point changed from Spennymoor 400kV Substation to Wearside Connection Node D 400kV Substation
- 28 Feb 2025 registerCapacity changed from 330 MW to 300 MW
- 28 Feb 2025 registerConnection date moved from 30 Oct 2035 to 30 Oct 2034 (−12 months)
- 30 Jul 2024 registerAdded to the register
Also at Wearside Connection Node D 400kV Substation
Substation view3 other projects, 1.3 GW still to connect at this substation in total.