Low Carbon Energy Centre BESS Joyce Green Lane
NET ZERO MARINE SERVICES LIMITED at Littlebrook 132kV Substation
- Connection date
- 31 Oct 2037
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 250 MW
- Connected now
- 0 MW
- Still to connect
- 250 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Embedded
- Region
- England and Wales
- Project number
- PRO-003540
- In the register since
- March 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 24 Dec 2024 registerConnection date moved from 30 Oct 2027 to 31 Oct 2037 (+120 months)
- 26 Mar 2024 registerAdded to the register
Also at Littlebrook 132kV Substation
Substation view1 other project, 550 MW still to connect at this substation in total. 300 MW is due to connect here before this project’s connection date of 31 Oct 2037.