Littlebrook BESS
- Connection date
- 15 Oct 2027 +3 months since 9 Dec
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 300 MW
- Connected now
- 0 MW
- Still to connect
- 300 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Embedded
- Region
- England and Wales
- Project number
- PRO-001832
- In the register since
- November 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 11 Aug 2026 registerConnection date moved from 15 Jul 2027 to 15 Oct 2027 (+3 months)
- 19 Dec 2025 registerConnection point changed from Littlebrook 400kV Substation to Littlebrook 132kV Substation
- 29 Aug 2025 registerCustomer changed from ECODEV GROUP LTD to ECODEV (SOUTH) LTD
- 23 Dec 2022 registerSubstation name updated in the register (from Littlebrook 400kV to Littlebrook 400kV Substation)
- 29 Nov 2022 registerAdded to the register
Also at Littlebrook 132kV Substation
Substation view1 other project, 550 MW still to connect at this substation in total.