L48 BESS Burnside
- Connection date
- 31 Oct 2033
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-003063
- In the register since
- August 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 19 Jun 2026 registerConnection point changed from New deer 275kV to New Deer 2 132kV Substation
- 1 May 2026 registerCustomer changed from Lower 48 Energy BESS Limited to S4 UK DEV LTD
- 31 Mar 2026 registerMarked as Gate 1
- 28 Mar 2025 registerConnection point changed from New Deer 2 132kV Substation to New deer 275kV
- 29 Aug 2023 registerAdded to the register
Also at New Deer 2 132kV Substation
Substation view1 other project, 375 MW still to connect at this substation in total.