Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

S4 UK DEV LTD

Customer named in the TEC register

4projects in the register
795 MWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

Projects

ProjectConnection siteTechnologyQueued MWConnection dateGateStatus
L48 BESS BurnsideNew Deer 2 132kV SubstationStorage20031 Oct 2033Gate 1Scoping
L48 BESS Dams of CraigieL48 BESS Dams of CraigieStorage with solar or wind22031 Oct 2033Gate 1Scoping
L48 BESS Glen AppL48 BESS GLEN APP 275/132KV SUBSTATIONStorage20031 Oct 2033 +60 moGate 1Scoping
UPPER GREENFIELDS BESSNew Deer 2 132kV SubstationStorage17531 Oct 2033Gate 1Scoping

Recent changes

  • L48 BESS Glen AppSouth Scotland, StorageConnection date moved from 30 Oct 2028 to 31 Oct 2033 (+60 months)+60 mo
  • UPPER GREENFIELDS BESSNorth Scotland, StorageConnection date moved from 31 Oct 2032 to 31 Oct 2033 (+12 months)+12 mo
  • L48 BESS Glen AppSouth Scotland, StorageConnection date moved from 31 Oct 2028 to 30 Oct 2028 (1 day earlier)
  • UPPER GREENFIELDS BESSNorth Scotland, StorageConnection date moved from 31 Oct 2033 to 31 Oct 2032 (−12 months)−12 mo
  • L48 BESS BurnsideNorth Scotland, StorageConnection point changed from New deer 275kV to New Deer 2 132kV Substation
  • L48 BESS Glen AppSouth Scotland, StorageSubstation name updated in the register (from L48 BESS Glen App to L48 BESS GLEN APP 275/132KV SUBSTATION)
  • L48 BESS Glen AppSouth Scotland, StorageMarked as Gate 1
  • L48 BESS Dams of CraigieNorth Scotland, Storage with solar or windMarked as Gate 1
  • L48 BESS BurnsideNorth Scotland, StorageCustomer changed from Lower 48 Energy BESS Limited to S4 UK DEV LTD
  • L48 BESS Dams of CraigieNorth Scotland, Storage with solar or windCustomer changed from Lower 48 Energy BESS Limited to S4 UK DEV LTD
  • L48 BESS Glen AppSouth Scotland, StorageCustomer changed from Lower 48 Energy BESS Limited to S4 UK DEV LTD
  • UPPER GREENFIELDS BESSNorth Scotland, StorageCustomer changed from Lower 48 Energy BESS Limited to S4 UK DEV LTD
  • L48 BESS BurnsideNorth Scotland, StorageMarked as Gate 1
  • UPPER GREENFIELDS BESSNorth Scotland, StorageMarked as Gate 1
  • UPPER GREENFIELDS BESSNorth Scotland, StorageRenamed from [23-0225] UPPER GREENFIELDS - 175MW BESS
  • UPPER GREENFIELDS BESSNorth Scotland, StorageConnection point changed from New Deer 2 400kV Substation to New Deer 2 132kV Substation
  • L48 BESS BurnsideNorth Scotland, StorageConnection point changed from New Deer 2 132kV Substation to New deer 275kV
  • UPPER GREENFIELDS BESSNorth Scotland, StorageAdded to the registerNew
  • L48 BESS Glen AppSouth Scotland, StorageAdded to the registerNew
  • L48 BESS BurnsideNorth Scotland, StorageAdded to the registerNew
  • L48 BESS Dams of CraigieNorth Scotland, Storage with solar or windConnection point changed from Energy Storage System;PV Array (Photo Voltaic/solar) to L48 BESS Dams of Craigie
  • L48 BESS Dams of CraigieNorth Scotland, Storage with solar or windAdded to the registerNew
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO