East Claydon High Impact Green Energy Hub (HIGEH) 1
EAST CLAYDON STORAGE LIMITED at East Claydon 400kV Substation
- Connection date
- 6 Dec 2036 +25 months since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Nuclear + Solar + Reactive compensation + Onshore wind
- Total capacity
- 1,000 MW
- Connected now
- 0 MW
- Still to connect
- 1,000 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002652
- In the register since
- July 2023
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerConnection date moved from 31 Oct 2034 to 6 Dec 2036 (+25 months)
- 16 Jun 2026 registerMarked as Gate 1
- 29 Aug 2025 registerCustomer changed from TELIS ENERGY UK LIMITED to EAST CLAYDON STORAGE LIMITED
- 28 Jul 2023 registerAdded to the register
Also at East Claydon 400kV Substation
Substation view5 other projects, 4.1 GW still to connect at this substation in total. 2.7 GW is due to connect here before this project’s connection date of 6 Dec 2036.
- East Claydon StorageEAST CLAYDON STORAGE LIMITED, Storage, Gate 1Oct 2026500 MW
- RosefieldRosefield Energyfarm Limited, Storage with solar or wind, Not statedOct 2031500 MW
- East Claydon Green Energy CentreEAST CLAYDON GREEN NG LIMITED, Storage with solar or wind, Not statedOct 20341 GW
- East Claydon Greener Grid ParkEast Claydon Energy Limited, Storage, Gate 1Nov 2034650 MW
- Alderton PV & BESS StationBNRG ALBION LIMITED, Storage with solar or wind, Gate 1Oct 2037450 MW