J212 High Grove Solar
RWE Renewables UK Solar and Storage Limited at Thetford 400kV Substation
- Connection date
- 31 Oct 2031
- Gate
- Not stated
- Status
- Awaiting Consents
- Planning consent
- Pre-application
High Grove Solar (EN0110010) · Source: Planning Inspectorate - Technology
- Storage + Solar
- Total capacity
- 720 MW
- Connected now
- 0 MW
- Still to connect
- 720 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002542
- In the register since
- April 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Jul 2025 registerConnection point changed from Necton 400kV Substation to Thetford 400kV Substation
- 27 Feb 2024 registerCustomer changed from JBM SOLAR LIMITED to RWE RENEWABLES UK SOLAR AND STORAGE LIMITED
- 29 Sep 2023 registerCustomer changed from DALIA HOLDINGS LTD to JBM SOLAR LIMITED
- 30 May 2023 registerCustomer changed from JBM SOLAR PROJECTS (UK) LTD to DALIA HOLDINGS LTD
- 28 Apr 2023 registerAdded to the register
Also at Thetford 400kV Substation
Substation viewNo other projects in the register at this connection point.