Inchbean Energy Park
BROCKWELL STORAGE & SOLAR LIMITED at Kilmarnock Town 275/33kV Substation
- Connection date
- 8 Feb 2027
- Gate
- Gate 2
- Status
- Consented
- Technology
- Storage
- Total capacity
- 60 MW
- Connected now
- 0 MW
- Still to connect
- 60 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Embedded
- Region
- South Scotland
- Project number
- PRO-002453
- Tracked since
- 14 Aug 2026
Change history
Every change to this project across 9 registers from 14 Aug 2026 to 21 Sep 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Consented
Also queued at Kilmarnock Town 275/33kV Substation
Substation viewNo other projects in the register at this connection point.