Inchbean Energy Park
BROCKWELL STORAGE & SOLAR LIMITED at Kilmarnock Town 275/33kV Substation
- Connection date
- 8 Feb 2027 +19 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Planning consent
- Granted 19 Jun 2025
Scottish Government (S36), reference ECU00004968 · Source: REPD - Technology
- Storage
- Total capacity
- 60 MW
- Connected now
- 0 MW
- Still to connect
- 60 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Embedded
- Region
- South Scotland
- Project number
- PRO-002453
- In the register since
- August 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Consents Approved
- 19 Jun 2026 registerConnection date moved from 30 Jun 2025 to 8 Feb 2027 (+19 months)
- 19 Jun 2026 registerGiven a Gate 2 connection offer
- 5 Jun 2026 registerSubstation name updated in the register (from Kilmarnock Town 275/33kV to Kilmarnock Town 275/33kV Substation)
- 27 Sep 2024 registerSubstation name updated in the register (from Kilmarnock Town GSP to Kilmarnock Town 275/33kV)
- 28 Jun 2024 registerCustomer changed from RNA-ENERGY LTD to BROCKWELL STORAGE & SOLAR LIMITED
- 29 Aug 2023 registerAdded to the register
Also at Kilmarnock Town 275/33kV Substation
Substation viewNo other projects in the register at this connection point.