Flemyland Battery Storage
- Connection date
- 27 Apr 2029 +18 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Planning consent
- Granted 6 Dec 2024
Scottish Government (S36), reference ECU00004984 · Source: REPD - Technology
- Storage
- Total capacity
- 100 MW
- Connected now
- 0 MW
- Still to connect
- 100 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-002360
- In the register since
- March 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Consents Approved
- 29 May 2026 registerTechnology changed from Demand, Storage to Storage
- 5 May 2026 registerConnection date moved from 26 Oct 2027 to 27 Apr 2029 (+18 months)
- 5 May 2026 registerGiven a Gate 2 connection offer
- 27 Sep 2024 registerConnection point changed from Kilwinning to Kilwinning 132/33kV
- 28 Jul 2023 registerSubstation name updated in the register (from Kilwinning 132kV Substation to Kilwinning)
- 31 Mar 2023 registerAdded to the register
Also at Kilwinning 132/33kV
Substation view2 other projects, 190 MW still to connect at this substation in total. 90 MW is due to connect here before this project’s connection date of 27 Apr 2029.