Benthead Solar
- Connection date
- 3 Apr 2025
- Gate
- Gate 2
- Status
- Consents Approved
- Planning consent
- Granted 11 Aug 2023
Scottish Government (S36), reference ECU00004702 · Source: REPD - Contract for Difference
- Allocation Round 6
- Technology
- Storage + Solar
- Total capacity
- 63 MW
- Connected now
- 0 MW
- Still to connect
- 63 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Embedded
- Region
- South Scotland
- Project number
- PRO-001881
- In the register since
- December 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 24 Sep 2026 registerStatus changed from Scoping to Consents Approved
- 24 Sep 2026 registerGiven a Gate 2 connection offer
- 7 Jul 2026 registerConnection point changed from Kilwinning GSP to Kilwinning 132/33kV
- 23 Dec 2022 registerAdded to the register
Also at Kilwinning 132/33kV
Substation view2 other projects, 190 MW still to connect at this substation in total.