Middleton BESS
Middleton Energy Storage Limited at Middleton 400KV Substation
- Connection date
- 31 May 2029 +30 months since 9 Dec
- Gate
- Gate 2
- Status
- Under Construction/Commissioning
- Technology
- Storage
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002305
- In the register since
- July 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 1 Oct 2026 registerConnection date moved from 30 Nov 2026 to 31 May 2029 (+30 months)
- 1 Oct 2026 registerStatus changed from Scoping to Under Construction/Commissioning
- 1 Oct 2026 registerGiven a Gate 2 connection offer
- 23 Dec 2022 registerCustomer changed from KONA ASSET 1 LIMITED to Middleton Energy Storage Limited
- 23 Dec 2022 registerSubstation name updated in the register (from Middleton 400KV to Middleton 400KV Substation)
- 29 Jul 2022 registerAdded to the register
Also at Middleton 400KV Substation
Substation view2 other projects, 840 MW still to connect at this substation in total. 400 MW is due to connect here before this project’s connection date of 31 May 2029.