Heysham Green Energy Centre
- Connection date
- 30 Oct 2028
- Gate
- Not stated
- Status
- Awaiting Consents
- Technology
- Storage + Solar
- Total capacity
- 400 MW
- Connected now
- 0 MW
- Still to connect
- 400 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001710
- In the register since
- December 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Aug 2025 registerCustomer changed from INNOVA RENEWABLES LIMITED to HEYSHAM GREEN NG LIMITED
- 29 Jul 2025 registerConnection point changed from Heysham 400kV Substation to Middleton 400KV Substation
- 29 Apr 2025 registerCustomer changed from HEYSHAM GREEN NG LIMITED to INNOVA RENEWABLES LIMITED
- 28 Mar 2025 registerCustomer changed from INNOVA RENEWABLES LIMITED to HEYSHAM GREEN NG LIMITED
- 29 Jul 2022 registerConnection point changed from Heysham to Heysham 400kV Substation
- 31 Dec 2021 registerAdded to the register
Also at Middleton 400KV Substation
Substation view2 other projects, 840 MW still to connect at this substation in total.