Sellindge Grid Stability Services
SELLINDGE GRID SERVICES LIMITED at Sellindge 400kV Substation
- Connection date
- 11 Aug 2026 (0 MW)
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Reactive compensation
- Total capacity
- 0 MW
- Connected now
- 0 MW
- Still to connect
- 0 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002206
- In the register since
- April 2022
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Apr 2025 registerConnection date moved from 2 Jul 2026 to 11 Aug 2026 (+1 month)
- 28 Mar 2025 registerConnection date moved from 31 Oct 2025 to 2 Jul 2026 (+8 months)
- 28 Nov 2023 registerConnection date moved from 29 Aug 2025 to 31 Oct 2025 (+2 months)
- 28 Nov 2023 registerStatus changed from Scoping to Consents Approved
- 30 Jun 2023 registerCustomer changed from WP GRID SERVICES 11 LIMITED to SELLINDGE GRID SERVICES LIMITED
- 23 Dec 2022 registerSubstation name updated in the register (from Sellindge 400kV to Sellindge 400kV Substation)
- 29 Apr 2022 registerAdded to the register
Also at Sellindge 400kV Substation
Substation view2 other projects, 576 MW still to connect at this substation in total.