Rochester Renewable Project
- Connection date
- 22 Sep 2028
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Solar + Onshore wind
- Total capacity
- 60 MW
- Connected now
- 0 MW
- Still to connect
- 60 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002097
- In the register since
- January 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 24 Dec 2024 registerConnection point changed from Kingsnorth GSP to Kingsnorth 132kV Substation
- 31 Jan 2023 registerAdded to the register
Also at Kingsnorth 132kV Substation
Substation view1 other project, 180 MW still to connect at this substation in total.