Whitehill Battery Storage
- Connection date
- 30 Oct 2028 +16 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Planning consent
- Granted 28 Oct 2024
Scottish Government (S36), reference ECU00004632 · Source: REPD - Technology
- Storage
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-002093
- In the register since
- September 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Awaiting Consents to Consents Approved
- 1 May 2026 registerConnection date moved from 30 Jun 2027 to 30 Oct 2028 (+16 months)
- 1 May 2026 registerGiven a Gate 2 connection offer
- 2 Jan 2026 registerConnection point changed from Easterhouse 275/33kV to Easterhouse 275kV
- 27 Jun 2025 registerConnection date moved from 31 Oct 2026 to 30 Jun 2027 (+8 months)
- 27 Sep 2024 registerConnection point changed from Easterhouse 275kV to Easterhouse 275/33kV
- 30 Sep 2022 registerAdded to the register
Also at Easterhouse 275kV
Substation viewNo other projects in the register at this connection point.