Whitehill Battery Storage Ltd
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Whitehill Battery Storage | Easterhouse 275kV | Storage | 200 | 30 Oct 2028 +16 mo | Gate 2 | Consents Approved |
Recent changes
- Whitehill Battery StorageSouth Scotland, StorageStatus changed from Awaiting Consents to Consents Approved
- Whitehill Battery StorageSouth Scotland, StorageConnection date moved from 30 Jun 2027 to 30 Oct 2028 (+16 months)+16 mo
- Whitehill Battery StorageSouth Scotland, StorageGiven a Gate 2 connection offerGate 2
- Whitehill Battery StorageSouth Scotland, StorageConnection point changed from Easterhouse 275/33kV to Easterhouse 275kV
- Whitehill Battery StorageSouth Scotland, StorageConnection date moved from 31 Oct 2026 to 30 Jun 2027 (+8 months)+8 mo
- Whitehill Battery StorageSouth Scotland, StorageConnection point changed from Easterhouse 275kV to Easterhouse 275/33kV
- Whitehill Battery StorageSouth Scotland, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?