South Kyle 2 Wind farm
VATTENFALL WIND POWER LTD at South Kyle 2 132/33kV Substation
- Connection date
- 31 Jul 2030
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Onshore wind
- Total capacity
- 92.4 MW
- Connected now
- 0 MW
- Still to connect
- 92.4 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-001963
- In the register since
- July 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 7 Apr 2026 registerMarked as Gate 1
- 29 Oct 2024 registerCapacity changed from 67 MW to 92.4 MW
- 29 Oct 2024 registerConnection date moved from 25 May 2029 to 31 Jul 2030 (+14 months)
- 27 Feb 2024 registerConnection point changed from New Cummock 132/33kV Substation to South Kyle 2 132/33kV Substation
- 29 Aug 2023 registerCapacity changed from 81 MW to 67 MW
- 29 Aug 2023 registerConnection date moved from 13 Apr 2029 to 25 May 2029 (+1 month)
- 23 Dec 2022 registerSubstation name updated in the register (from New Cummock 132/33kV to New Cummock 132/33kV Substation)
- 29 Jul 2022 registerAdded to the register
Also at South Kyle 2 132/33kV Substation
Substation viewNo other projects in the register at this connection point.