Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / South Scotland

Cloud Hill Windfarm

Cloud Hill Windfarm Limited at Glenglass 132/33kV

Connection date
31 May 2030
Gate
Not stated
Status
Awaiting Consents
Planning consent
Granted 16 Dec 2025
Scottish Government (S36), reference ECU00003461 · Source: REPD
Technology
Storage + Onshore wind
Total capacity
60 MW
Connected now
0 MW
Still to connect
60 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Direct Connection
Region
South Scotland
Project number
PRO-001938
In the register since
June 2022

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Stages

StageConnected MWAdds MWCumulative MWDateGateStatus
10505031 May 2030Not statedAwaiting Consents
20106031 Oct 2036Not statedScoping

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 29 Jul 2025 register
    Stage 1: Technology changed from Storage to Storage, Onshore wind
  • 29 Jul 2025 register
    Stage 2: Technology changed from Storage to Storage, Onshore wind
  • 30 May 2025 register
    Connection point changed from Cloud Hill Wind Farm 132kV Substation to Glenglass 132/33kV
  • 30 May 2025 register
    Stage 2: Technology changed from Onshore wind to Storage
  • 30 May 2025 register
    Restructured from 1 stage (50 MW from 30 Sep 2028) to 1 stage (50 MW from 31 May 2030). First connection date +20 months
  • 29 Apr 2025 register
    New stage added (10 MW from 31 Oct 2036)
  • 30 Jun 2022 register
    Added to the register

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO

Planning consent

The planning decision or stage for this project, from DESNZ’s Renewable Energy Planning Database (REPD), July 2026 edition, with the planning authority and its reference. QueueWatch matched the project to that record. NESO’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.