Twentyshilling Wind Farm
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Planning consent
- Granted 23 Dec 2019
Dumfries and Galloway, reference 18/0206/FUL · Source: REPD - Technology
- Onshore wind
- Total capacity
- 37.8 MW
- Connected now
- 37.8 MW
- Still to connect
- 0 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-001365
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Sep 2024 registerSubstation name updated in the register (from Glenglass 132/33kV Substation to Glenglass 132/33kV)
- 23 Dec 2022 registerSubstation name updated in the register (from Glenglass 132/33kV to Glenglass 132/33kV Substation)
- 29 Oct 2021 register37.8 MW now connected
- 29 Oct 2021 registerStatus changed from Under Construction/Commissioning to Built
- 30 Mar 2021 registerConnection date moved from 30 Jan 2021 to 21 May 2021 (+4 months)
Also at Glenglass 132/33kV
Substation view2 other projects, 60 MW still to connect at this substation in total.