Cruachan Expansion
Drax Cruachan Expansion Limited at Cruachan 275kV Substation
- Connection date
- 31 Oct 2030
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Granted 21 Jul 2023
Scottish Government (S36), reference ECU00004492 · Source: REPD - Technology
- Pumped storage
- Total capacity
- 600 MW
- Connected now
- 0 MW
- Still to connect
- 600 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-001889
- In the register since
- April 2022
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 31 Oct 2023 registerConnection date moved from 30 Sep 2030 to 31 Oct 2030 (+1 month)
- 29 Apr 2022 registerAdded to the register
Also at Cruachan 275kV Substation
Substation view1 other project, 640 MW still to connect at this substation in total. 40 MW is due to connect here before this project’s connection date of 31 Oct 2030.