Projects / South Scotland
Connection date
4 Apr 2029 +22 months since 14 Aug
Gate
Gate 2
Status
Consented
Technology
Pumped storage
Total capacity
480 MW
Connected now
440 MW
Still to connect
40 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Direct Connection
Region
South Scotland
Project number
PRO-000113
Tracked since
14 Aug 2026

Stages

StageConnected MWAdds MWCumulative MWDateGateStatus
14400440NoneNot statedBuilt
20404804 Apr 2029Gate 2Consented

Change history

Every change to this project across 9 registers from 14 Aug 2026 to 21 Sep 2026.

  • 21 Sep 2026 register
    Stage 2: Status changed from Scoping to Consented
  • 21 Sep 2026 register
    Stage 2: Given a Gate 2 connection offer
  • 28 Aug 2026 register
    Stage 2: Connection date moved from 1 Jun 2027 to 4 Apr 2029 (+22 months)

Also queued at Cruachan 275kV Substation

Substation view

1 other project, 640 MW still to connect at this substation in total.