- Connection date
- 31 Oct 2033
- Gate
- Not stated
- Status
- Scoping
- Technology
- Offshore wind
- Total capacity
- 495 MW
- Connected now
- 0 MW
- Still to connect
- 495 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-001766
- In the register since
- February 2022
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 Jan 2026 registerConnection point changed from Talisk Offshore Wind Farm to Arnish Lewis Hub 400kV Substation
- 29 Aug 2025 registerCustomer changed from MAGNORA OFFSHORE WIND AS to MAGNORA OFFSHORE WIND N3 LIMITED
- 29 Aug 2025 registerConnection point changed from New Dounreay to Talisk Offshore Wind Farm
- 27 Feb 2024 registerConnection point changed from REVIEW - New Dounreay to New Dounreay
- 30 Jan 2024 registerConnection point changed from New Dounreay to REVIEW - New Dounreay
- 30 Mar 2022 registerConnection point changed from Arnish to New Dounreay
- 25 Feb 2022 registerAdded to the register
Also at Arnish Lewis Hub 400kV Substation
Substation view1 other project, 1.4 GW still to connect at this substation in total. 900 MW is due to connect here before this project’s connection date of 31 Oct 2033.