Spiorad Na Mara Offshore Wind Farm
SPIORAD NA MARA LIMITED at Arnish Lewis Hub 400kV Substation
- Connection date
- 31 Dec 2030
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Application submitted 11 Mar 2026
Marine Scotland · Source: REPD - Technology
- Offshore wind
- Total capacity
- 900 MW
- Connected now
- 0 MW
- Still to connect
- 900 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-001642
- In the register since
- October 2021
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 Jan 2026 registerConnection point changed from NPI C 220/66KV OFFSHORE SUBSTATION to Arnish Lewis Hub 400kV Substation
- 27 Jun 2025 registerCapacity changed from 740 MW to 900 MW
- 27 Jun 2025 registerConnection date moved from 31 Oct 2030 to 31 Dec 2030 (+2 months)
- 24 Dec 2024 registerCustomer changed from Northland Power UK Limited to SPIORAD NA MARA LIMITED
- 29 Dec 2023 registerRenamed from NPI C Offshore Wind Farm
- 28 Nov 2023 registerConnection date moved from 31 Oct 2033 to 31 Oct 2030 (−36 months)
- 28 Feb 2023 registerRenamed from NPI C 220/66kV Offshore
- 29 Oct 2021 registerAdded to the register
Also at Arnish Lewis Hub 400kV Substation
Substation view1 other project, 1.4 GW still to connect at this substation in total.