WindyHill Energy Storage Facility
- Connection date
- 31 Dec 2027 +28 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Storage
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-001696
- In the register since
- November 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 23 Jun 2026 registerConnection date moved from 27 Aug 2025 to 31 Dec 2027 (+28 months)
- 23 Jun 2026 registerStatus changed from Scoping to Consents Approved
- 23 Jun 2026 registerGiven a Gate 2 connection offer
- 23 Dec 2025 registerConnection point changed from Windyhill 275/132kV to Windyhill 132kV
- 21 Nov 2025 registerCustomer changed from ENERGYGRIDPOWER LTD to Windyhill Grid 1 LTD
- 29 Oct 2024 registerConnection date moved from 30 Jul 2024 to 27 Aug 2025 (+13 months)
- 27 Sep 2024 registerConnection point changed from Windy Hill Grid 132kV Substation to Windyhill 275/132kV
- 23 Dec 2022 registerSubstation name updated in the register (from Windy Hill Grid 132kV to Windy Hill Grid 132kV Substation)
- 30 Jun 2022 registerCapacity changed from 150 MW to 200 MW
- 30 Nov 2021 registerAdded to the register
Also at Windyhill 132kV
Substation viewNo other projects in the register at this connection point.