Windyhill Grid 1 LTD
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| WindyHill Energy Storage Facility | Windyhill 132kV | Storage | 200 | 31 Dec 2027 +28 mo | Gate 2 | Consents Approved |
Recent changes
- WindyHill Energy Storage FacilitySouth Scotland, StorageConnection date moved from 27 Aug 2025 to 31 Dec 2027 (+28 months)+28 mo
- WindyHill Energy Storage FacilitySouth Scotland, StorageStatus changed from Scoping to Consents Approved
- WindyHill Energy Storage FacilitySouth Scotland, StorageGiven a Gate 2 connection offerGate 2
- WindyHill Energy Storage FacilitySouth Scotland, StorageConnection point changed from Windyhill 275/132kV to Windyhill 132kV
- WindyHill Energy Storage FacilitySouth Scotland, StorageCustomer changed from ENERGYGRIDPOWER LTD to Windyhill Grid 1 LTD
- WindyHill Energy Storage FacilitySouth Scotland, StorageConnection date moved from 30 Jul 2024 to 27 Aug 2025 (+13 months)+13 mo
- WindyHill Energy Storage FacilitySouth Scotland, StorageConnection point changed from Windy Hill Grid 132kV Substation to Windyhill 275/132kV
- WindyHill Energy Storage FacilitySouth Scotland, StorageSubstation name updated in the register (from Windy Hill Grid 132kV to Windy Hill Grid 132kV Substation)
- WindyHill Energy Storage FacilitySouth Scotland, StorageCapacity changed from 150 MW to 200 MW
- WindyHill Energy Storage FacilitySouth Scotland, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?