Zenobe Norton
- Connection date
- 31 Oct 2031
- Gate
- Gate 1
- Status
- Awaiting Consents
- Technology
- Storage
- Total capacity
- 150 MW
- Connected now
- 0 MW
- Still to connect
- 150 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001691
- In the register since
- November 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 22 May 2026 registerMarked as Gate 1
- 29 Aug 2025 registerConnection point changed from Norton 400kV Substation to Norton East 400kV Substation
- 30 Mar 2022 registerSubstation name updated in the register (from Norton to Norton 400kV Substation)
- 30 Nov 2021 registerAdded to the register
Also at Norton East 400kV Substation
Substation view4 other projects, 1.6 GW still to connect at this substation in total.
- NortonENSO GREEN HOLDINGS X LIMITED, Storage with solar or wind, Gate 1Oct 2032400 MW
- Letch Beck Energy ParkRenewable Energy Systems Limited, Storage with solar or wind, Gate 1Oct 2033600 MW
- Grindon GrangeSTARLIGHT ENERGY UK LIMITED, Storage with solar or wind, Not statedOct 2035240 MW
- Lightsource Norton East PVLightsource Renewable UK Development Limited, Storage with solar or wind, Gate 1Oct 2035240 MW