Cellarhead 400kV Energy Storage
- Connection date
- 13 Sep 2028 +14 months since 9 Dec
- Gate
- Gate 2
- Status
- Under Construction/Commissioning
- Technology
- Storage
- Total capacity
- 300 MW
- Connected now
- 0 MW
- Still to connect
- 300 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001685
- In the register since
- September 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 22 Oct 2026 registerStatus changed from Awaiting Consents to Under Construction/Commissioning
- 22 Oct 2026 registerGiven a Gate 2 connection offer
- 1 Oct 2026 registerConnection date moved from 16 Jul 2027 to 13 Sep 2028 (+14 months)
- 29 Jul 2025 registerConnection date moved from 30 Jun 2026 to 16 Jul 2027 (+13 months)
- 29 Oct 2024 registerConnection date moved from 30 May 2024 to 30 Jun 2026 (+25 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Cellarhead 400KV to Cellarhead 400kV Substation)
- 28 Sep 2021 registerAdded to the register
Also at Cellarhead 400kV Substation
Substation view3 other projects, 1.4 GW still to connect at this substation in total.