Projects / South Scotland
Connection date
30 Apr 2026
Gate
Gate 2
Status
Scoping
Technology
Storage
Total capacity
450 MW
Connected now
0 MW
Still to connect
450 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Direct Connection
Region
South Scotland
Project number
PRO-001551
Tracked since
14 Aug 2026

Stages

StageConnected MWAdds MWCumulative MWDateGateStatus
10505018 May 2026Gate 2Consented
2010015030 Apr 2026Not statedScoping
3030045030 Oct 2037Not statedScoping

Change history

Every change to this project across 9 registers from 14 Aug 2026 to 21 Sep 2026.

No changes since 14 Aug 2026. Follow this project to see the next one on your watchlist.

Also queued at Coylton 275kV substation

Substation view

No other projects in the register at this connection point.